Buying a faster corrugator is expensive. Recovering lost minutes on the line you already have is often cheaper and quicker. Here are five places to start.

Why Minutes Matter

Take a line at 200 m/min and 2.5 m wide, which makes 500 m² per minute. Suppose an 8-hour shift loses 30 minutes to setup, 20 minutes to paper changes and 30 minutes to stops. Effective running time is only 400 minutes.

Recovering just 20 of those lost minutes at 90% efficiency adds:

20 × 500 × 0.9 = 9,000 m² per day

Over 26 working days, that is 234,000 m² per month.

1. Cut Changeover Time

Group similar orders, prepare the next job in advance and use written setup procedures. Fewer and shorter changeovers raise effective time directly.

2. Reduce Paper Breaks and Reel Change Stops

Torn paper stops production. Check reel quality, storage and handling, and look at the stability of your mill roll stand.

3. Maintain Equipment Before It Fails

Planned maintenance, timely replacement of worn parts and regular calibration reduce unexpected stops. A scheduled 30-minute service costs less than an unplanned two-hour breakdown.

4. Fix Quality Problems at the Source

Defects such as delamination and flute crush marks mean rework, scrap and stoppages. Solving them raises usable output, not just machine speed.

5. Measure and Review Every Month

Track effective running time, downtime reasons, changeover count and actual output. Review them with your operators, since they often know where the minutes go.

Know When Equipment Is the Answer

If your data shows the line is already running efficiently and demand still outgrows it, then upgrading or expanding makes sense. At that point you will have the evidence to choose the right width, speed and configuration, as covered in the guide to new vs. used corrugator equipment.